Looking at a career as a certified Project Management Professional (PMP)? This Cheat Sheet gives you quick, handy PMP certification facts to remember on test day to help you answer exam questions. You can review major project management concepts; key tools, techniques, outputs, and processes; and and some common equations found on the exam. Many key terms are defined in the Project Management Body of Knowledge (PMBOK) Guide Glossary.
If you begin your exam preparation now, the PMP® Exam will be based on PMBOK® Guide 5th edition by the PMP® Exam update. Summary: PMI updates the PMBOK® Guide and the PMP® Exam every several years as the practices of project management evolves. The new PMBOK® Guide edition (i.e. The 6th edition) has been published in the 3rd quarter of 2017. The PMP Process Chart: About the Chart. The process chart is assembled in a table like format. It contains 6 columns for the 5 process groups (or project phases) and 11 rows for the 10 knowledge areas (plus one row and column for headers). As I make the chart (table) in this blog, practice along with me on an extra sheet of paper.
Understand Scheduling Relationships for the PMP Certification Exam
When you’re ready to take the PMP (Project Management Professional) Certification exam, expect to see up to ten questions dealing with network diagrams, precedence diagramming, and scheduling issues. Here are some PMP details you need to know:
FS = Finish-to-start
FF = Finish-to-finish
SS = Start-to-start
SF = Start-to-finish
Lead = The amount of time an activity can be advanced with respect to a predecessor activity
Lag = The amount of time a successor activity is required to be delayed with respect to a predecessor activity
A mandatory dependency is based on the nature of the work.
A discretionary dependency is based on a best practice or preferred way of doing something.
An external dependency is based on relationships outside the project.
Dec 19, 2019. May 25, 2019. Cms software download for mac.
An internal dependency is based on dependencies inside the project.
PMP Certification: 4 Estimating Techniques for Project Managers
You can apply PMP (project management professional) estimating techniques to resources, effort, duration, and costs. PMPs use different methods of estimating, depending on the situation.
Estimating method | Description |
---|---|
Analogous estimating | Generally used at the start of the project when not much is known. Compares the current project with past similar projects. A quick and relatively easy method of estimating, although not terribly accurate. |
Parametric estimating | Used for estimates that are quantitatively based, such as dollars per square foot or number of installations per day. A relatively simple method, but not every activity or cost can be estimated quantitatively. |
Three-point estimating | Accounts for uncertainty associated with estimating by determining an optimistic (best case, represented by O), most likely (represented by M), and pessimistic (worst case, represented by P) scenario. The most likely estimate is weighted most heavily. The equation is |
Bottom-up estimating | Used when there is significant detail about the activity. A detailed assessment of the resources, capabilities, and amounts are used to determine an accurate duration or cost estimate. This is the most accurate method but also the most time-consuming and expensive form of estimating. |
PMP Exam: Statistics for Normal and Cumulative Distributions
PMPs (project management professionals) often apply basic statistics to their projects. Minecraft price pc. For the PMP certification exam, here’s what you need to know when dealing with normal and cumulative distributions:
Equations are based on a normal distribution. In a normal distribution, keep the following in mind:
The b3 is a flatted 3 and you flat a note by moving one fret toward the nut. Bass chords pdf. Yep the chord formula chart told me that.Now if you would prefer a chart for every type of chord check this out.I prefer to memorize one chart - The Major Scale Box - and then adjust it for what I need to make. Want the Cm7 chord. Use which ever one you like best.Looking at the box; where is the b3? It's spelling is R-b3-5-b7.
68.3% of the data points fall within one standard deviation.
95.5% of the data points fall within two standard deviations.
99.7% of the data points fall within three standard deviations. Mac taskbar download for windows 7.
If you’re looking at a normal curve and need a cumulative distribution, you should remember these values:
professional conduct. parental rights. The ethics of teaching fifth edition pdf. democracy. religious differences. teacher burnout.
0.15% of the data points fall between 0 and –3 from the mean.
2.25% of the data points fall between 0 and –2 from the mean.
16% of the data points fall between 0 and –1 from the mean.
84% of the data points fall between 0 and +1 from the mean.
Jul 27, 2009 Here is a video showcasing some of the new features: Scratch Live version 1.9.1: This is the first maintenance release for Scratch Live 1.9. This version includes many core improvements, feature enhancements, and bug fixes - including a greatly expanded SP-6 Sample Player. Serato scratch live 1.9.1 download pc. The original and unrivaled vinyl emulation software for professional DJs. Scratch Live is vinyl emulation software that operates exclusively with Rane hardware. Mix and scratch digital music on your computer with Serato Control Vinyl or Control CDs.
97.75% of the data points fall between 0 and +2 from the mean Buy windows 8 disk.
99.85% of the data points fall between 0 and +3 from the mean.
PMP Certification: 6 Strategies for Conflict Resolution
Experienced project management professionals (PMPs) know that as they plan and execute projects, they’ll encounter conflicts and differences of opinion. As you study for your PMP certification exam, become familiar with these six strategies to resolve conflict.
Strategy | Description | Situation |
---|---|---|
Confronting / Problem-solving | Confronting the conflict as a problem to be solved | When you have confidence in the other party’s ability to problem solve When the relationship is important When you need a win-win solution |
Collaborating | Win-win through collaboration and meeting to resolve issues | When there is time and trust When the objective is to learn When you want to incorporate multiple views When there is time to come to consensus |
Compromising | When you are looking for some degree of satisfaction for both parties | When there is a willingness to give and take When both parties need to win When you can’t win When an equal relationship exists between the parties in conflict When the stakes are moderate To avoid a fight |
Smoothing / Accommodating | Emphasize areas of agreement | To reach an overarching goal To maintain harmony When any solution will be adequate When you will lose anyway To create goodwill |
Forcing | Win-lose; impose the resolution | When you are right In a do-or-die situation When the stakes are high To gain power If the relationship is not important When time is of the essence |
Withdrawal / Avoiding | Retreat; cool off | When you can’t win When the stakes are low To preserve neutrality or reputation If the problem will go away on its own |
PMP Earned Value: Variances and Indexes
On the PMP certification exam, you’ll see five to ten questions on variances and indexes. Free principles of marketing 17th edition pdf. Here’s fundamental information that project managers need to determine cost and schedule variances and indexes.
For variance and indexes, always start with EV.
When looking for information on schedule, use PV.
When looking for information on cost, use AC.
For a variance, subtract.
SV = EV – PV
CV = EV – AC
Negative is bad; positive is good.
For an index, divide.
SPI = EV / PV
CPI = EV / AC
Less than 1.0 is bad, greater than 1.0 is good.
8 Quality Control Tools to Know for PMP Certification
There are many ways to assess quality control, and professional project managers (PMPs) make good use of them. When you take the PMP certification exam, you should be able to apply the following quality control tools:
Step 1: Download Mac CleanerFirst of all, download Mac Cleaner on your computer and finish the installation by dragging the icon to Application.Step 2: Launch Mac CleanerNow launch this software on your Mac after you install the program successfully. Then it will detect your Mac OS system status automatically. You can find the program as the following screenshot.Step 3: Choose uninstall appIn the main interface, you can see the key features from the left side of the window. How do i delete a downloaded app on my mac. Then choose Uninstaller to delete applications on MacBook Pro.
Pmp Version 6 Chart For Kids
Cause and effect diagram. Diagrams that define the inputs to a process or product in order to identify potential causes of defects.
Middle click on the Plus button to activate it.- Many optimization on SAO Menu to remove CPU usage.- The voicebox had been changed to support more player. For more info, open up the music1.ini- SAO HP-Bar had been changed to switch between CPU, RAM, and hard disc C, D, E when clicked.- IPPing had been changed so that when clicked, ping will be recalculated and change the display between WAN and LAN ip. Download rainmeter sao for android phone. SAO Menu Style 0.7First download the Rainmeter from here.installing, download the repackaged SAO Rainmeter Skin from below,The skin,rmskin package(recommended for easier usage, one click install, backup your layout before using),may install directly from rmskin package, and select the SAO layout for basic SAO menu, OR install manually from the first link. There's many tutorial on how to do this and I will not be explaining those, go learn how to use Rainmeter.SAO Menu Style 0.7This SAO Menu Skin Pack is made by 9SunThis Skin Pack is a modification on many Sword Art Online Skin Pack I found on the web.Features added:- An option.ini for setting up the SAO Menu.
Histogram. A bar chart showing a distribution of variables.
Final fantasy 9 mac download. Watch real-time status of tasks by phase, track progress, and compare budgeted hours and costs vs.
Run chart. Show trends in the variation of a process over time.
Scatter diagram. Shows the relationship between two variables.
Control chart. A graphic display of process data over time and against established control limits, and that has a centerline that assists in detecting a trend of plotted values toward either control limit.
Jan 16, 2020 The process to install software on a Mac is slightly different than on a Windows machine, but it’s still straightforward. There are three main methods to install software on a Mac: Manual install: After you download a disk image file with the DMG extension, double-click it to mount it. A window pops up with an app icon in it (and maybe a. We bought all new MacBook Pros and bootcamped them into Windows 7 laptops. This is around 2013-2014. This was an incredible combination! The hardware quality of Mac with the ubiquitous software support of Microsoft Windows. This was a very stable, very powerful and reliable laptop. I ran my 2013 MacBook Pro as a Windows 7 machine right up to 2019! Switching from windows to mac software developer. Mar 21, 2019 Of course, with Parallels, you can use ScreenFlow to record both Mac and Windows screens. The Windows-based screen recorders don't have that option because VMs on Windows won't run Mac software. Long-term Windows users looking to dip their toe into the Mac ecosystem for the first time typically stick to applications they are familiar with on PC, but there is a wealth of other software.
Flowcharting. The depiction in a diagram format of the inputs, process actions, and outputs of one or more processes within a system.
Pareto chart. A histogram, ordered by frequency of occurrence, that shows how many results were generated by each identified cause. https://walkernew573.weebly.com/blog/can-you-download-with-spotify-premium.
Inspection. Examining or measuring to verify whether an activity or a component, product, result, or service conforms to specified requirements.